Transmission Tower Retrofit Survey: A How-To Guide

Surveyor holding a handheld LiDAR scanner beside a steel transmission tower, with an RTK GNSS pole nearby.

A 2024 US study found that upgrading existing power lines by replacing their wires costs about half as much as building new lines for the same capacity. But every upgrade starts with a transmission tower retrofit survey: accurate data on each tower’s shape, steel condition, and position on the line. This guide shows how to collect that data from the ground in five steps, so the work can continue when flights are restricted.

Key takeaways

  • A tower inspection before a retrofit captures three things in one visit: the 3D shape of the tower and its span clearances, the condition of the steel, and the exact position of the tower on the line grid.
  • The data goes to your engineers’ PLS-CADD model. Surveys collect and deliver the data. Your engineers do the analysis and redesign.
  • Ground-based collection needs no flights. It uses handheld or terrestrial LiDAR, ground-level NDT, and RTK GNSS.

Why tower inspection matters before a retrofit

Many power lines are old, and the cost of keeping them running is rising. Analysis by the Bank of America Institute, reported by Fortune in August 2025, found that 31% of US transmission lines are past their useful life. In 2024, 67% of US transmission and distribution spending went to replacing and upgrading equipment. That is about SAR 236 billion (USD 63 billion), compared with about SAR 120 billion (USD 32 billion) for new lines and substations.

Upgrading also saves money. The same 2024 study from GridLab and the UC Berkeley Goldman School estimated USD 85 billion in system savings by 2035. That is about SAR 319 billion. Note that this study looks at replacing the wires on existing lines. It does not study tower retrofit surveys directly, but it shows why utilities choose to upgrade what they already have.

Time is the second reason. RMI reports that upgrade projects inside an existing corridor can often finish in one to three years. Utility Dive notes that new lines can take five to 15 years to build. In the US, a 2026 Atlantic Council report says getting a permit for a new line takes about six and a half years on average, before construction starts. If the survey is slow, it eats into the time you save by upgrading.

Safety is the third reason. The US Bureau of Labor Statistics recorded that 21 electrical power-line installers and repairers died at work in 2024, a rate of 13.8 per 100,000 workers. The same BLS table shows that the rate for all US workers was 3.3. So power-line work is about four times riskier. Ground-based collection does not remove this risk, but it keeps survey crews at ground level instead of on the structure.

Saudi Arabia has the same need, at a larger scale. Saudi Energy’s transmission network grew 6% in one year to 110,950 circuit kilometers by the third quarter of 2026. MEED reported a plan to expand the network to about 160,000 km by 2030. Saudi Electricity Company has announced a plan to invest SAR 500 billion by 2030 in transmission networks. One market research report puts grid investment in 2025 at SAR 88.2 billion. Every kilometer added today will need upgrade surveys later.

Before engineers can redesign a tower, they need accurate as-built data. A retrofit survey gives them that. In the life of a transmission line, it sits at the last stage:

  1. Planning and route selection
  2. Construction
  3. Commissioning
  4. Operation and maintenance (O&M)
  5. Pre-summer peak maintenance
  6. Rehabilitation and upgrade (this guide)

How to run a tower inspection before a retrofit: 5 steps

In this guide, tower inspection means collecting data on the tower’s shape, steel condition, and position. It does not include engineering analysis or redesign. Here are the five steps.

Step 1: Agree on the scope and access

Start with the engineering team. Agree on the list of towers, the line grid reference, and how the crew will reach each site. Ask for the existing drawings and the version of the PLS-CADD model that the team uses. Agree the file formats for the delivered data at the same time.

Also agree on what is not in scope. Terra Drone Arabia does not do engineering analysis or redesign, route planning, or live-line work. Writing this down at the start avoids confusion later. Check permits and site access rules for each tower before the crew travels.

Step 2: Scan the tower members and span clearances with LiDAR

Point cloud of a lattice transmission tower in orange and blue dots, with dotted scan lines from a handheld LiDAR scanner.
A point cloud shows the real shape of each tower member.

LiDAR stands for light detection and ranging. A LiDAR scanner sends out laser pulses and measures how long each one takes to return. The result is a point cloud: millions of 3D points that show the real shape of the tower.

We use the FJD Trion S2, a high-precision LiDAR scanner from FJDynamics. Handheld LiDAR lets a surveyor walk around the tower while scanning. Terrestrial LiDAR scans from fixed positions on the ground. Both capture the tower members (the steel angles and braces), the joints, and the clearances between the wires, the tower, and the ground or nearby objects.

Why use a scan for a retrofit? Your engineers can measure any member from the point cloud on their computer. They do not need to return to site to check one missing dimension. The scan shows how the tower is built today, which can differ from the old drawings.

Scan accuracy: the manufacturer lists a relative accuracy of 1.2 cm for the FJD Trion S2, measured in test conditions. Accuracy on site depends on the tower, the weather, and how the scan is run. Scan time per tower depends on tower height, width, and access, so it is confirmed in the quote for your tower list.

Step 3: Run ground-level NDT

Non-destructive testing (NDT) checks the condition of a structure without damaging it. For a tower inspection before a retrofit, ground-level NDT has three parts:

  • UT thickness: ultrasonic testing (UT) sends sound waves through the steel and measures how thick it is now. Corrosion makes steel thinner, so this tells engineers how much steel is left.
  • Coating check: this shows whether the protective coating (such as galvanizing or paint) is intact.
  • Foundation check: a check of the condition of the base and footings. Only the parts that are visible from the ground can be checked.

Ground-level NDT reaches the base and the lower members. Members higher up the tower are captured by the LiDAR scan for shape and clearance, but not for thickness. If your engineers need thickness readings higher up, that needs a different method, and you should agree it before the survey starts. NDT time per tower depends on how many readings your engineers ask for, so it is confirmed in the quote.

Diagram of a transmission tower. The whole tower is marked for LiDAR scan, and the lower part is marked for ground-level NDT, with a technician placing a probe on a leg.
The scan covers the whole tower. Ground-level NDT covers the base and lower members.

Working from the ground keeps the crew off the structure for most of the work. It reduces time at height. It does not remove all risk, and the crew still follows the site’s safety rules.

Step 4: Tie everything to the line grid with RTK GNSS

A scan and a thickness table are only useful if every tower sits in the right place. Real-time kinematic (RTK) positioning, using a global navigation satellite system (GNSS), corrects satellite positions in real time. We use the FJD Trion V10i, a multi-constellation RTK system, to set the position of each tower on the line grid.

This gives all the data one shared coordinate frame. The LiDAR scan, the NDT readings, and the existing line model then line up. For the V10i, the manufacturer lists an RTK accuracy of 8 mm + 1 ppm horizontal and 15 mm + 1 ppm vertical. The “ppm” part adds 1 mm of error for every kilometer from the base station, so over 1 km that is about 9 mm horizontal and 16 mm vertical. Tree cover, nearby steel, and a poor satellite view can change what you get in the field.

Step 5: Deliver the data to the PLS-CADD model

Flow diagram: LiDAR scan, ground-level NDT, and RTK GNSS feed one data package, which goes to the engineering team's PLS-CADD model and then to structural redesign.
TDSA delivers the data. Your engineers take it into PLS-CADD for the redesign.

PLS-CADD is the line design software that many utility engineers use. The engineering team brings the data into its own PLS-CADD model and uses it for the structural redesign.

A survey delivers the data in a form the team can load. The deliverables are:

  • a registered point cloud for each tower;
  • a thickness and coating table for each tower;
  • a coordinate report that links every tower to the line grid.

After delivery, your engineers take over. We can answer questions about how the data was collected.

What you get, and what upgrading is worth

Deliverables

 

Deliverable Format What the engineer uses it for
Registered point cloud .las, .ply, .pts, or .e57 (formats the FJD Trion S2 exports) Measure members, check clearances, update the tower model
Thickness and coating table A spreadsheet or CSV file, agreed with your engineers Check the condition of the steel and the coating
Coordinate report A table or PDF, agreed with your engineers Place each tower on the line grid

 

Is a ground-based tower inspection right for you?

It fits when:

  • flights are restricted, or a flight permit would take too long;
  • the towers can be reached by road or track;
  • your engineering team already works in PLS-CADD and needs data for a redesign.

It does not fit when:

  • you need engineering analysis or a redesign.
  • you need route planning for a new line;
  • the work needs live-line access.

What you need to provide: the list of towers, the line grid reference, existing drawings, site access and permits, and the PLS-CADD model version.

Need a tower inspection before your retrofit?

Frequently asked questions

What is a transmission tower retrofit survey?

It is the data collection done before a tower is upgraded. It records the tower’s shape, the condition of its steel, and its position on the line. Engineers use this data to redesign the tower.

Can you inspect towers if drones cannot fly?

Yes. Handheld or terrestrial LiDAR, ground-level NDT, and RTK GNSS all work from the ground. No flight is needed.

What data goes into PLS-CADD, and in what format?

The engineering team receives a point cloud, a thickness and coating table, and a coordinate report for each tower. The FJD Trion S2 exports point clouds as .las, .ply, .pts, and .e57. Agree the exact formats with your engineers at the start (Step 1).

How long does a survey take per tower?

It depends on the tower height, the access, and how many NDT readings your engineers ask for, so one figure does not fit every line. We confirm the time per tower in the quote, after we see your tower list.

Table of Contents

Share This Article

Data you can trust, Operations you can scale

Ready to Transform Your Operations?

Latest Insights

Aerial drone view of Riyadh skyline in Saudi Arabia

Get the Drone & Geospatial Brief, Saudi Arabia

Real project breakdowns, GACA regulatory updates, and field-tested case studies from oil and gas, mining, and infrastructure operations. Used by engineering and procurement teams at Saudi Arabia’s largest operators. 

Joined by 2K+ industry professionals in Saudi Arabia.